From Monday 5 January until the end of January 2026, the Net Zero Energy Project contractor, Vital Energi, will be carrying out ground investigations and district heating repairs in the north west area of Lancaster Square.
These investigations and repairs are required to locate and identify an existing fault with the District Heating leak detection system.
- Part of the Lancaster Square steps will remain open, but the accessible ramp will be out of use. An accessible diversion route will be in place around the Great Hall Complex and Music Building. View the route on Mazemap.
- There is not expected to be any disruption to heating or hot water in the local area.
- Work will progress between 8am – 5pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
- Dates can be subject to change.
From mid-December 2025, work will be taking place to connect the Welcome Centre to the campus District Heat Network as part of the Net Zero Energy Project. This work will be noisy at times and some accessible parking spaces and cycle parking will be affected.
Enabling works from 15 – 19 December 2025
From Monday 15 – Friday 19 December FRS Roofing Services will be carrying out works to enable the installation of District Heating pipework into the Welcome Centre rooftop plantroom.
- Tower scaffolding will be erected outside the Welcome Centre to allow the removal of some brickwork and existing roof lights.
- Bin stores and cycle parking in the area will remain open.
- There will be limited disruption to rooms A04, A04a and A04b in the Welcome Centre during this work.
Building connection works from 5 January – 7 April 2026
From Monday 5 January – Tuesday 7 April 2026 the Net Zero Energy Project contractor, Vital Energi, will be working on the replacement of the existing boilers, with a district heating pipework connection from the Bowland Main plantroom into the Welcome Centre rooftop plantroom.
- Bin stores will remain open.
- There will be no heating in the Welcome Centre between 8am – 5pm on Tuesday 10 February 2026 during the replacement of the boilers and connection of the district heating pipework into the plantroom. The hot water supply will not be affected.
- Work will progress between 8am – 5pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
- Dates can be subject to change.
The Net Zero Energy Project contractor, Vital Energi, is currently working on the installation of the external pipework and the replacement of the boilers at County Field accommodation. This work is scheduled to complete by mid-December 2025.
- Scaffolding has been erected at one side of each block of houses to enable the contractor to install new pipes to the elevation of the building.
- There are temporary footpath closures in the local area, and diversion signage is in place. Access to the accommodation buildings will be maintained at all times.
- Bin stores, secure cycle parking and the BBQ area remain accessible.
- In December, the contractor will be removing the scaffolding in two phases:
- Houses 78 – 87: Monday 1 – Friday 5 December
- Houses 88 – 106: Monday 15 – Friday 19 December
- Parking spaces will be taken out of use temporarily on North Drive to allow for scaffolding collection.
- Work will progress between 8am – 5pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
- Dates can be subject to change.