From Monday 21 July to Tuesday 30 September 2025 the Net Zero Energy Project contractor, Vital Energi, will be working on the pipework connections in the plant room on the ground floor of the County Main building.
- During the work, a temporary boiler located on County Avenue will be used to maintain essential services to the building until a one-time, 48-hour shutdown of hot water. This will take place from 8.00am on Monday 21 until 5pm on Wednesday 22 July. The hot water supply in the family flats will not be affected.
- Access will be closed along the footpath from Lancaster Square to County Avenue throughout the works. Diversion signage and Heras fencing will be in place to allow the installation and connection of the District Heating Network to the plant room.
- 6 parking bays will be out of use on County Avenue from Monday 21 July until Monday 11 August for the storage of materials. The electric vehicle and accessible parking bays will be unaffected.
- Access to County South kitchens from County Avenue will remain open for deliveries.
- Work will commence from 8.00am - 5pm and will be noisy at times. The project webpages list alternative study spaces if required.
On Wednesday 16 April, the Net Zero Energy Project contractor, Vital Energi, will complete the installation of the district heating pipework up to County Field accommodation and move towards building connection works from Tuesday 22 April until Friday 19 September 2025.
External pipework will be installed on the end elevation of each block of houses and along the rooftop to the existing boiler flue, connecting the buildings to the District Heating Network. This is in preparation for the final pipework connections and installation of new Heat Interface Units starting in July 2025.
- Scaffolding will be erected at one end of each block of houses to enable the contractor to install the pipework and access the rooftop. Heras fencing and diversions will be in place.
- Access will be closed along the footpath between Apple House (building 84) and Violet House (building 85) from the south side, and the footpath between Tansy House (building 87) and Sorrel House (building 88) will be closed from both sides. Access to building entrances will always be maintained via diversion routes where necessary.
- This work will be noisy at times while scaffolding is assembled and intermittent drilling is carried out. The project webpages list alternative study spaces if required.
- Working hours are 8am to 5pm Monday to Friday.
- Bin stores and secure cycle parking will remain accessible.
- The BBQ area will remain open.
- The dog spend area will remain out of use.
- Four staff parking spaces along North Drive will be taken out of use during the work but will be reopened as soon as the work completes.
- An additional eight staff parking spaces opposite County Field accommodation and eight staff parking spaces opposite the CEH building will be taken out of use intermittently during the work.
From Wednesday 2 April – Friday 11 July 2025 the Net Zero Energy Project contractor, Vital Energi, will be working on the installation of the district heating pipework from outside County Main plant room across County Avenue and up to County South Anglezarke (building number 75).
- Access will be closed along the footpath from Lancaster Square to County Avenue throughout the works. Diversion signage and Heras fencing will be in place to enable the contractor to safely dig trenches for the installation of new District Heating pipework.
- The work may be noisy at times, the project webpages list alternative student study space if required.
- Working hours are 8am to 5pm Monday to Friday.
- The bin store will be temporarily relocated to the east end of County Avenue.
- The secure bike parking will remain open for use.
- Two accessible parking spaces at the west end of County Avenue will be temporarily out of use during the works, however two additional accessible parking spaces will be created on the south side of County Avenue.
- Access to County South kitchens from County Avenue will remain open for deliveries except for Saturday 12 April when the road will be completely closed, excavated, and new district heating pipework installed. The Avenue will re-open on Monday 15 April.
